2005 ~ 2006  Hong Kong

Causeway Bay Flyover Demolition

 

It is proposed to remove 100 m x 8 m prestressed structure across Victoria Park Road for widening of Victoria Park Road. The demolition sequence can be separated into 4 stages :

Stage 1 - Advance Works (Propping)

Stage 2 - Demolition of Composite Tee

                Beams, Staircase & Temporary ramp

Stage 3 - Demolition of Vehicle Bridge &

                Footbridge

Stage 4 - Demolition of Diaphragm Beams, Piers

                &  Platform

 

Before Demolition:


Stage1 stage2 stage2 stage3 stage4